Implementation of the second phase of the production line of Siman Mand Dashti factory

PC implementation of the production line from the stone crusher to the cement mill feeders is being set up

* Implementation of 65,000 cubic meters of concrete pouring and all construction and construction operations of the production line and architecture of the buildings.
* Construction and installation of about 4000 tons of metal structures of the production line
* The construction of a fully preheated concrete structure with a height of 120 meters within 13 months
* Full implementation of stone crusher and soil hall from soil removal to start-up within 24 months
* Execution of 16 thousand square meters of metal skeleton covering of the production line and 12 thousand square meters of equipment isolation
* Supplying about 3100 tons of domestically made mechanical machines
* Installation of about 5600 tons of production line machines
* Supply and installation of installation items including: Air, water and fueling the production line
* Purchase of about 200 tons of foreign machines
* Fireproofing the production line
* Start-up and stabilization services for the entire production line
* Operation of the production line for 4 years

Majd Khaf cement project

Project management responsibility in the form of contract management

* Having the responsibility of managing the employer of the project with full delegation of the authority of the employer, including concluding contracts and purchasing goods and services
* Construction and installation of about 1700 tons of metal structures
* Execution of 43,000 cubic meters of concrete pouring in the concrete structures of the production line
* Conclusion of the first complete production line contract in the cement industry with China
* Buying foreign machines from Chinese and European companies
* Implementation of the factory's own 132 kV double-circuit power transmission line
* Construction and supply of mechanical, electrical and control equipment from clinker silos to the end of the production line
* Implementation of the main station of the factory with the full capacity of one million tons of cement line
* Implementation of the project with good quality and low cost
* Managing the operation, maintenance and repairs of the first phase of the production line after the launch for one year
* Doing things related to following up the activation of the second phase of the project

First phase cemented plain

* Supplying mechanical equipment for domestic production of about 800 tons
* Supply of production line facilities, installation and commissioning of mechanical equipment and facilities of about 3000 tons
* Construction of the remaining metal skeleton of the first phase of about 250 tons
* Installation of the remaining metal skeleton of the first phase of about 350 tons

Darab cement

* Implementation of the main electrofilter of the production line including:
Civil, metal structures, architecture, installation and commissioning
* Construction of mechanical equipment and installation and commissioning of the third cement silo
* Dismantling the worn out main chimney of the factory and installing a new chimney in a repair operation for 25 days
* Dismantling the worn clinker transfer belt and replacing it with a new clinker transfer belt

Green Gilan cement

* Setting up the cement production line and stabilizing the production and operation of the factory in the form of a consortium with Azarkhak and Lian Sanat companies.
* Recruiting, training and organizing manpower to be used in the production line

Executive operations of the Pigeon Nest Department of Tehran Cement Complex

The implementation of the pigeon nest project of the sixth unit of the Tehran cement complex, including the implementation of the concrete structure, the construction and installation of the metal skeleton, the construction and installation of mechanical equipment and its commissioning in a period of 2 months, in such a way that in the Mustafafan Foundation, this project is considered as a jihadi plan. He was named Sal.

New Fars cement

Carrying out the implementation of the installation and commissioning of the factory's new loading dock

Rafsanjan golden cement

Carrying out the implementation of the conversion of open circuit cement into closed circuit

Joint implementation of dust removal projects with FLSairtech

1- Converting the electro filters of Unit 6 of Tehran Cement Complex with the participation of FLSairtech company in the form of design, sea transportation and clearance, construction and installation of internal equipment, complete implementation of mechanical and electrical installations and launching the entire project.
2- Dismantling of old electrofilters and complete implementation of conversion operations within 37 days

Kurdistan Cement

Construction of Asia Cement equipment, Lushe design, with a capacity of 125 tons

Zabul cement project

Managing the completion of executive operations and leading the start-up and recruitment and training of human resources and structuring.

Deshstan cement project

* Implementation of silvi concrete structure of the third cement factory with a diameter of 16 meters and a height of 54 meters of Abiao design with a volume of 6500 cubic meters of concrete pouring
* Construction of mechanical equipment inside the cement silo
* Installation and commissioning of silvi equipment of the building

Bukan Cement

Project management and engineering activities for the construction of Bukan cement factory up to the start-up stage of phase one (starting cement production)

Children's gold processing factory

Implementation of the production line of the concrete department, construction, installation and operation of the factory

Khavaf iron concentrate factory

Implementation of the production line of the concrete department, construction, installation and operation of the factory

Zagros White Cement Factory

Implementation of the foundation of the concrete structures of the production line of the project

Sepo Cement Factory

Implementation of the foundation of the concrete structures of the production line of the project

Chabahar Tis Cement Project

1- Implementation of fireproofing operations of the baking department of the cement factory

2- Carrying out the services of setting up the machines of the production line of the cement factory

Persian Gulf Saroj Lian Lime Project

1- Implementation of the concrete part of multi-purpose office buildings (bank and security building)

2- Implementation of the architectural operation of the factory guest house building

3- Implementation of the structures of the concrete part of the production line of the factory

4- Implementation of construction and installation of mechanical equipment

5- Implementation of fireproofing operation of the double shaft furnace department

Corrective design project for material transfer, Unit 8, Tehran Cement Complex

The implementation of the raw material transfer line project through a conveyor belt with a length of about 500 meters includes:

Executive operations of the concrete department, steel frame structure, construction and installation of mechanical equipment, implementation of electrical installations, and setting up of the corrective transmission line department.